uu/quarter Public holiday (calendar day) Working days (working hours Mon-Fri) Working hours (Mon-Fri) Working hours (exceptions)
January 01 January – New Year (T)* 22 176
February 24 February – Anniversary of the Republic of Estonia (P)* 20 160 If 23.veebrar IS a working day, then hours worked per month 160-3=157
March 21 168
Total 1st quarter 2 public holidays 63 504 504-3=501
April 19 April – Good Friday (Fri)21 April – Easter Day (Fri) 21 168
May 01 May – Spring Festival (Mon) 22 176
June 9 June – Pentecost 1 (Fri)23 June – Victory Day (Fri)*
24 June – Midsummer Day (Mon)
19 152 If 22 June is a working day, then 152-3=149 hours worked per month.
2nd quarter total 6 public holidays 62 496 496-3=493
July 23 184
August 20 August – Independence Day (T) 21 168
September 21 168
III quarter total 1 public holiday 65 520
October 23 184
November 21 168
December 24 December – Christmas Eve (T)*
25 December – Christmas Day (Mon)
26 December – Christmas Day (Sun)
19 146 If 23 OR 31 December is NOT a working day, then hours worked per month 146+3=149If 23 AND 31 December are NOT a working day, then hours worked per month 146+6=152.
IV quarter total 3 public holidays 63 498 498+3=501 / 498+6=504
2016 TOTAL 12 public holidays, 8 of them on working days (Mon-Fri) 253 2018

* Pursuant to § 53 of the Employment Contracts Act and the Holidays and Festivals Act, the working day preceding New Year’s Day, the anniversary of the Republic of Estonia, Victory Day and Christmas Eve is shortened by three hours.

Number of working weeks per year: 50,60

Average:
Number of working days per month: 21,08
Number of working hours per week: 39,88
Number of working hours per month: 168,17